Accounts-Activities

Position of D&AR cases to end of the month of JULY-2019

Major
Total No. Of casesNo. of cases to whom C/sheet has been issued for more than 03 monthsStatus of the caseReasons for delay in finalization and expected dates of finalization
NilNilNilNil
Minor
Total No. of casesStatus of casesReason for delay in finalization and expected dates of finalization
Date of issue of C/sheetNo. of cases under inquiryNo. of cases wherein I.O. report receivedNo. of cases under finalization (NIP to be issued)
NILN.A.N.A.N.A.N.A.N.A.

Position of Court Cases to end of JULY-2019

S.No.ItemsComments/Remarks
1No. of court cases 05
2No. of contempt01
3Total court cases 05
4 Cases where orders are yet to be implementedNIL
5Reasons for contempt and delay in implementation Since implemented & Afidavit filed in Hon’ble High Court/LKO
6Total cases decided in the last one yearNIL
7Decided in favour of Rlys.NIL
8Decided against RlysNIL

Position of PF Section to end of the month of JULY-2019

S.No.ItemsComments/Remarks
1Month due for monthly PF postingJune 19.
2Month of PF posting doneJune 19.
3Arrear with reasonsNIL
4Month of monthly reconciliation dueMarch 19.
5Month of monthly reconciledMarch 19.
6Arrear NIL
7Position of Annual reconciliationReconciliation of 2016-17 has been done and 2017-18 is in hand

Position of New Pension Scheme To End Of The Month Of JULY-2019

ItemParticulars of ItemPosition
Submission of FormTotal No. of Employee who joined on or after 01.01.042080
Total No. of Employee under NPS Scheme2080
No. of PRAN forms deposited with NSDL collection centre.2080
Status of AccountsNo. of closed and inactive Accounts74
No. of inactive Accounts Flagged74
Difference (2.2-2.1) and reasonsNIL
PRAN KitsNo. of PRAN Kits received from NSDL2078
No. of PRAN Kits distributed2078
Difference (3.2-3.1) and reasonsNIL
GrievancesNo. of grievances received from NSDLNIL
No. of grievances solvedNIL
No. of multiple PRAN generation case received from NSDLNIL
No. of multiple PRAN cases solvedNIL
No. of multiple PRAN cases pending and reason thereofNIL
BalanceBalances in major head 8342 in unit (reconciled with Books)NIL
Uploading of Subscriber Contributory Funds (SCF)SCFs uploaded for the month of June-19NIL
Total No. of files uploaded in the month of June-191
Total No. of files matched on the month of June-191

Details of Fraud, Losses and Theft Cases

No. of cases
( Less than Rs. 50,000.00)
No. of cases
( More than Rs.50,000.00)
Total
No. of casesAmountNo. of casesAmountNo. of casesAmount
0648841023823175* Plus 295000**073872016
* Losses due to fire in log-yard during 5/98. Dy. COS or Dy. CMM/AMV has sent the case to Dy. COS/IC, B.House New Delhi for write off. The amount is Rs. 42,61,280 as per FIR lodged in the case but the actual amount is Rs. 38,23,175.00, which has been sent for write off vide letter No: 144-S/write off statement/AMV/SL dated 14.08.2008
**Case of loss due to sale of serviceable electric loco bogie during the year 1995 of Rs. 295000/- has again been included vide H.Q. No. 2009/Effy/Fraud/Loss & Theft Dt. 06-11-2015

Position Of Implementation Of IPAS

 

Phase ? 1 Implemented w.e.f. 01.07.15. successfully.

Phase – II ?Implemented w.e.f. 01.08.15. PPO are being generated through I-PAS.

Phase ? III Implemented w.e.f. 01.09.15. PF withdrawal and settlement are being processed through I-PAS.

Revenue account current is also being submitted on I-PAS.

E-PPO generation has also been started from October 2016.

Statement showing the Average Unit Cost

(Fig. In thousands)

YearPOHNPOHIOH
PCVOCVPCVOCV
2009-10870427146119264
2010-11909587196Nil296
2011-12953733260Nil280
2012-131120798243Nil280
2013-141187881243Nil311
2014-1513271029263Nil311
2015-161276929234Nil311
2016-171363990NilNil300
2017-1813721121258Nil313
2018-191633NilNilNil331

BUDGETORY POSITION

Demand wise expenditure against BP to end of ?June -2019 is as under:-

GrantBA for 2019-20B.P to end of 06/19 Actual Ex. to the end of 06/19Excess/ Saving on BP% Excess/Saving Exp. Of BP% Actual Exp. of BARemarks
3198913149185133771-15414-10.33%67.25%Minor
4159971200021422942278.52%133.91%Less Budget Allotment
61022571766928689829-77099-10.05%67.46%Minor
75845543841630861924543.90%107.92%Due to less budget allotment
8660949574247-710-14.32%64.26%TC not received from CB Workshop.
1115217 1141310053-1360-11.92%66.06%Due to less tution fees passed
1211489861690244084.74%78.54%Due to less budget allotment
131542291156721439622829024.46%93.34%Due to more retirement
Total148348011126121075394-37218-3.35%72.49%

CADER REVIEW POSITION TO END OF THE MONTH OF July- 2019

S.No.DesignationPay BandGrade PaySanctioned StrengthOn RollVacancy
1SO/SSO/Sr.ISA9300-348004800/5400221111
2ISA’s 9300-348004800/5400211
3SV’s9300-348004200523
4SSE/IT9300-348004200110
5JE/IT9300-348004200321
6AA9300-348004200512922
7JAA5200-202002800514
8A/C Clerk5200-202001900404
9Steno5200-202002400110
10Record Supplier5200-202001900202
11Record Sorter5200-202001800101
12Group-D5200-2020018001165
13Total1085454

POSITION OF INSPECTION REPORT

1: HQ. Inspection Report and outstanding para

S.No. Year of Inspection Report ParaClearedBalanceRemarks
1201217161Reply under preparation.

 

2: Railway Board Inspection Report and outstanding para

S.NoYear of Inspection ReportParaClearedBalanceRemarks
1200452 49 03Reply sent to HQ.
22009625606Reply sent to HQ.
32015803347Replies sent to HQ.